I have created a Scenario called 'validate input form against database'. This work involves a number of Tasks done by various members of the project team. How do I link these Tasks to the Scenario so that I can produce a report about number of hours work remaining before the Scenario is complete
Although I can relate task to a scenario (select scenerio in the All Scenarios report, right-click | Add Related Work Item) , it doesn't seeem to do much more than create a new task with a title that says 'related to work item 111 - validate input form against database'. Does this actually create a proper relationship between the Work Items that I can use in a query If I could create such a query this would solve my probem. How can it be done
Visual Studio Team System29
|