PostPosted: Tue May 01 17:39:16 CDT 2007 Top

Microsoft Project >> MS Project Hi

I have a MS Project 2000 and I have two questions (may be for beginners :-)

- How to enter a recurrent task that happens regularly?

- On the Gantt chart , can we see the summary recurrent task as a line that
includes milestones showed inside it (meaning the repeated tasks showed as
milestones inside the line that represents the recurrent summary task) ?

Thanks in advance

Fayez

DotNet183  
 
 
JulieS





PostPosted: Tue May 01 17:39:16 CDT 2007 Top

Microsoft Project >> MS Project Hi Fayez,

1) To create a recurring task choose Insert > Recurring task in the
menu.

2) I'm afraid not. The summary recurring task is not a long summary
task line like other summary tasks. You will see each occurance
appearing at the summary line.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project


"a" <EMail@HideDomain.com> wrote in message news:f189at$8dq$EMail@HideDomain.com...
> Hi
>
> I have a MS Project 2000 and I have two questions (may be for
> beginners :-)
>
> - How to enter a recurrent task that happens regularly?
>
> - On the Gantt chart , can we see the summary recurrent task as a line
> that includes milestones showed inside it (meaning the repeated tasks
> showed as milestones inside the line that represents the recurrent
> summary task) ?
>
> Thanks in advance
>
> Fayez
>


 
 
a





PostPosted: Wed May 02 10:10:41 CDT 2007 Top

Microsoft Project >> MS Project Thanks a lot

"JulieS" <passport6847 at maine dot rr dot com> wrote in message
news:%EMail@HideDomain.com...
> Hi Fayez,
>
> 1) To create a recurring task choose Insert > Recurring task in the menu.
>
> 2) I'm afraid not. The summary recurring task is not a long summary task
> line like other summary tasks. You will see each occurance appearing at
> the summary line.
>
> I hope this helps. Let us know how you get along.
>
> Julie
> Project MVP
>
> Visit http://project.mvps.org/ for the FAQs and additional information
> about Microsoft Project
>
>
> "a" <EMail@HideDomain.com> wrote in message news:f189at$8dq$EMail@HideDomain.com...
>> Hi
>>
>> I have a MS Project 2000 and I have two questions (may be for beginners
>> :-)
>>
>> - How to enter a recurrent task that happens regularly?
>>
>> - On the Gantt chart , can we see the summary recurrent task as a line
>> that includes milestones showed inside it (meaning the repeated tasks
>> showed as milestones inside the line that represents the recurrent
>> summary task) ?
>>
>> Thanks in advance
>>
>> Fayez
>>
>
>


 
 
JulieS





PostPosted: Wed May 02 12:45:17 CDT 2007 Top

Microsoft Project >> MS Project You're welcome Fayez, and thanks for the feedback.

Julie

"a" <EMail@HideDomain.com> wrote in message news:f1a9hp$iop$EMail@HideDomain.com...
> Thanks a lot
>
> "JulieS" <passport6847 at maine dot rr dot com> wrote in message
> news:%EMail@HideDomain.com...
>> Hi Fayez,
>>
>> 1) To create a recurring task choose Insert > Recurring task in the
>> menu.
>>
>> 2) I'm afraid not. The summary recurring task is not a long summary
>> task line like other summary tasks. You will see each occurance
>> appearing at the summary line.
>>
>> I hope this helps. Let us know how you get along.
>>
>> Julie
>> Project MVP
>>
>> Visit http://project.mvps.org/ for the FAQs and additional
>> information about Microsoft Project
>>
>>
>> "a" <EMail@HideDomain.com> wrote in message news:f189at$8dq$EMail@HideDomain.com...
>>> Hi
>>>
>>> I have a MS Project 2000 and I have two questions (may be for
>>> beginners :-)
>>>
>>> - How to enter a recurrent task that happens regularly?
>>>
>>> - On the Gantt chart , can we see the summary recurrent task as a
>>> line that includes milestones showed inside it (meaning the repeated
>>> tasks showed as milestones inside the line that represents the
>>> recurrent summary task) ?
>>>
>>> Thanks in advance
>>>
>>> Fayez
>>>
>>
>>
>
>